Bridge Street Bridge

November 9, 2011 Update

The bridge painting project remains behind schedule and there is no significant changes from the last update. The Selectboard has requested a representative from VTrans to appear at the November 21st meeting to explain what has happened and the future of the project.

October 25, 2011 Update

The bridge painting project is behind schedule. The original completion date was October 28th, however, that deadline will not be met. Work continues on the job but we are unsure of a new completion date. It is likely that the work will shut down for the Winter, and restart in the Spring. If that happens, all equipment will be removed from the Bridge for the duration of the shutdown, and the bridge will remain partially complete.

Naturally, this is not the result we expected. Work will continue until December 1st, when the State forbids any further work due to the Winter season.

September 9, 2011 Update

The painting contractor has begun to set up their equipment on the Bridge. Soon the temporary traffic signals will be installed and then the containment apparatus will go up, and one lane of the Bridge will be closed. At that time the pedestrian walkway will also be closed for the duration of the contract. Please be aware that morning traffic will be affected the most, so if you have an alternative route to work in the mornings we suggest that avoiding the Bridge will likely save you time during the project. Also, speed limits on East Hill Road and Kenyon Road have been temporarily reduced to 25mph due to the anticipated increase in traffic while the project is in action.

August 18, 2011 Update

The State of Vermont has hired Phoenix Development of Corfu, New York to paint the Bridge Street Bridge. Work is expected to begin the last week of August and continue until October 28th. In October of 2010 the Richmond Selectboard chose red to be the new color of the bridge. With the beginning of work, the bridge will be closed one late at a time, with a traffic light regulating traffic across the open lane. Expect travel delays during the work period from now until the project is complete.



Reports and Committee Documents
1997 AOT Historic Bridge Report - Richmond
1998 Historic Truss Bridge Plan
2006 Bridge Committee Mission Statement
2006 Bridge Street Bridge Informational Flyer
2006 CCS and Austin Bridge Repair Bids
2006 Hedges letter on bridge programming Oct 25
2006 Outline of Project Development Process
2006 Programming request from SB August
2006 Stantec's Inspection Report - July
2008 11-18 Preliminary Plan Amendment
2008 Biweekly Inspection 02-18
2008 Biweekly Inspection 11-18
2008 Biweekly Inspection 12-15
VTrans Inspection Report - 2004-12
VTrans Inspection Report - 2005-02
VTrans Inspection Report - 2005-10
VTrans Inspection Report - 2006-08
VTrans Inspection Report - 2007-03
VTrans Inspection Report - 2008-03

Minutes
02-26-09

Agendas
09-05-08

2007-2008 Scoping Process Documents
2008 Historic Bridge Agreement
2008 Finance and Maintenance Agreement
2008 02-05 Scoping Report - FINAL
2008 01-28 Committee Closure Letter & Recommendation
2007 11-12 Alternatives Presentation Minutes
2007 11-12 Alternatives - Aerial Views
2007 11-12 Alternatives Presentation
2007 11-12 Evaluation Matrix
2007 03-01 Scoping Process Tasks and Cost
2007 06-12 Project Alternatives
2007 05-14 Local Concerns Meeting Handout
2007 06-12 Purpose and Need Statemet
2006 Johnstone letter scoping Oct 16

 

PDF requires Adobe Acrobat Reader [Download Now]